| | | | | | | | STAFF REPORT - CITY COUNCIL/SUCCESSOR AGENCY/PUBLIC FINANCE AUTHORITY
| | |
| | | | | | | | Subject: | Authorize Assistant City Manager to Execute a Task Order with the City Engineer for Preliminary Engineering and Construction Engineering Services for the Cherry Lane Reconstruction Project | Meeting Date: | Thursday, August 18, 2022 | From: | Marissa Trejo, City Manager | Prepared by: | Sean Brewer, Assistant City Manager |
| | |
| | | | | | | | I. RECOMMENDATION:
Council Authorization for the Assistant City Manager to Execute a Task Order with the City Engineer for Preliminary Engineering and Construction Engineering Services for the Cherry Lane Reconstruction Project.
II. BACKGROUND:
The FY22 SB1 budget includes project funding for the removal of existing ac pavement, new ac pavement structural section reconstruction from 100’ east of Grant Street to Falcon Lane; includes new concrete curb & gutter segments, minor new sidewalk segment, new curb/median ADA ramps, new valley gutters, Manhole/Valve lids adjustments, bike lanes, crosswalks traffic striping and new AC Pavement Section Roadway Reconstruction for Cherry Lane.
III. DISCUSSION:
The City Engineer proposes to provide Civil Engineering Design & Construction Management Services for Cherry Lane between Falcon Lane and 100 feet east of Grant Street for a not to exceed amount of $136,300.00 The Cost estimate for construction is $591,000.00
IV. ALTERNATIVES:
- None at this time unless the council chooses not to proceed with the project.
V. FISCAL IMPACT:
This project will be funded partially by SB1 ($412,000) and the remainder by TDA - Street Maintenance. | | |
|