I.    RECOMMENDATION:

This item was requested as a Future Agenda Item by Mayor Lander. 

 

The City Manager recommends against the feasibility study due to the cost to the General Fund that is not budgeted.



II.    BACKGROUND:

The City of Coalinga received a request for temporary hangar installation at the Coalinga Municipal Airport. Staff provided some information received from neighboring airports about temporary hangars.

III.   DISCUSSION:

A feasibility study to develop the cost and requirements for temporary hangars could cost from $10,000 up to $50,000. These cost would be not be recovered upon the installation of the hangars, but may possibly increase the annual revenue if installation of temporary hangars is approved. 

IV.   ALTERNATIVES:



V.    FISCAL IMPACT:

The is an un-budgeted Airport expense that would come from the General Fund.